この記事の翻訳を準備しています。それまでの間、英語の原文を表示します。
規制と法律 · 2005/11/91 分で読めます
Basin Electric Power Cooperative, Inc.; Notice of Intent To Hold Public Scoping Meetings and Prepare an Environmental Impact Statement
ローカル自動翻訳 · 情報源の原言語
概要
The Rural Utilities Service (RUS) intends to hold public scoping meetings and prepare an environmental impact statement (EIS) in connection with possible impacts related to a project being proposed by Basin Electric Power Cooperative, Inc. (Basin Electric), of Bismarck, North Dakota. The proposal consists of the construction and operation of a coal-fired electric generation facility referred to as the Dry Fork Station, consisting of a single maximum net 385 Megawatt (MW) unit, at a site in Gillette, Wyoming, and the construction of 130 miles of 230 kilovolt (kV) transmission line in Campbell and Sheridan counties, referred to as the Hughes Transmission Project.
情報源の原言語: Federal Register — All Documents原文の発表を開く →