On September 23, 2014, the U.S. Nuclear Regulatory Commission (NRC) received the Post-Shutdown Decommissioning Activities Report (PSDAR) and the Site Specific Decommissioning Cost Estimate (DCE), dated September 23, 2014, for the San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. The PSDAR, which includes the DCE, provides an overview of Southern California Edison Company's (SCE's, or the licensee's) planned decommissioning activities, schedule, projected costs, and environmental impacts for SONGS Units 2 and 3. The NRC will hold a public meeting to discuss the PSDAR and DCE and receive comments.

来源原始语言: Federal Register — Nuclear Regulatory Commission打开原始公告 →