Energia e ambiente · 14/10/20141 min de leitura
Southern California Edison Company San Onofre Nuclear Generating Station, Units 2 and 3
Tradução automática local · Idioma original da fonte
Resumo
On September 23, 2014, the U.S. Nuclear Regulatory Commission (NRC) received the Post-Shutdown Decommissioning Activities Report (PSDAR) and the Site Specific Decommissioning Cost Estimate (DCE), dated September 23, 2014, for the San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. The PSDAR, which includes the DCE, provides an overview of Southern California Edison Company's (SCE's, or the licensee's) planned decommissioning activities, schedule, projected costs, and environmental impacts for SONGS Units 2 and 3. The NRC will hold a public meeting to discuss the PSDAR and DCE and receive comments.