Enerji ve çevre · 26.07.20211 dk okuma

Florida Power and Light Company; St. Lucie Plant, Unit No. 2

Yerel otomatik çeviri · Kaynağın orijinal dili

Özet

The U.S. Nuclear Regulatory Commission (NRC, or the Commission) has issued an exemption in response to a March 17, 2021, request from Florida Power and Light (FPL or the licensee). The approval permits a one-time schedular exemption to allow submittal of a license renewal application for the St. Lucie, Unit No. 2 facility earlier than 20 years before the expiration of the operating license, which expires on April 6, 2043.

Kaynağın orijinal dili: Federal Register — Nuclear Regulatory CommissionOrijinal duyuruyu açın →