In the Matter of Tennessee Valley Authority Bellefonte Nuclear Plant, Units 1 and 2
Локальный автоматический перевод · Язык оригинального источника
Краткое содержание
The U.S. Nuclear Regulatory Commission (NRC) has approved the Tennessee Valley Authority (TVA) requests to extend the latest construction completion dates for Bellefonte Nuclear Plant (BLN), Units 1 and 2, to October 1, 2021. TVA is the current construction permit (CP) holder for BLN, Units 1 and 2. The initial CPs for BLN were issued on December 24, 1974, authorizing TVA to construct BLN, Units 1 and 2, in Jackson County, AL.