In the Matter of Tennessee Valley Authority Bellefonte Nuclear Plant, Units 1 and 2
Traducción automática local · Idioma original de la fuente
Resumen
The U.S. Nuclear Regulatory Commission (NRC) has approved the Tennessee Valley Authority (TVA) requests to extend the latest construction completion dates for Bellefonte Nuclear Plant (BLN), Units 1 and 2, to October 1, 2021. TVA is the current construction permit (CP) holder for BLN, Units 1 and 2. The initial CPs for BLN were issued on December 24, 1974, authorizing TVA to construct BLN, Units 1 and 2, in Jackson County, AL.