Энергетика и окружающая среда · 11.10.20161 мин чтения
In the Matter of Southern Nuclear Operating Co., Inc.; Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2
Локальный автоматический перевод · Язык оригинального источника
Краткое содержание
The U.S. Nuclear Regulatory Commission (NRC) is issuing a confirmatory order (Order) to revise the Edwin I. Hatch Nuclear Plant Unit Nos. 1 and 2 (Hatch) National Fire Protection Association (NFPA) 805 License Amendment Request submittal date of October 4, 2016 to April 4, 2018. This new submittal date extends enforcement discretion until April 4, 2018, and supports the Southern Nuclear Operating Company, Inc. (the licensee) continued progress in activities related to the transition to NFPA 805.