エネルギーと環境 · 2025/10/21 分で読めます
NUREG: Guidelines for Inservice Testing at Nuclear Power Plants-Inservice Testing of Pumps and Valves and Inservice Examination and Testing of Dynamic Restraints (Snubbers) at Nuclear Power Plants
ローカル自動翻訳 · 情報源の原言語
概要
The U.S. Nuclear Regulatory Commission (NRC) is issuing NUREG- 1482, Revision 4, "Guidelines for Inservice Testing at Nuclear Power Plants--Inservice Testing of Pumps and Valves and Inservice Examination and Testing of Dynamic Restraints (Snubbers) at Nuclear Power Plants." NUREG-1482, Revision 4 provides a basic understanding of the regulatory basis for pump and valve inservice testing (IST) programs and dynamic restraint (snubbers) examination and testing programs. This NUREG also provides information regarding the NRC's involvement in the development of the American Society of Mechanical Engineers (ASME) Operation and Maintenance of Nuclear Power Plants, Division 1, OM Code: Section IST (OM Code).