Energia i środowisko · 22.01.19961 min czytania
Umetco Minerals Corporation; Notice of Opportunity for a Hearing
Automatyczne tłumaczenie lokalne · Oryginalny język źródła
Streszczenie
Notice is hereby given that the U.S. Nuclear Regulatory Commission (NRC) has received, by letters dated November 27, 1995, and January 4, 1996, an application from Umetco Minerals Corporation (Umetco) to amend License Condition (LC) 59 of Source Material License No. SUA-648 for the Gas Hills Wyoming uranium mill site. The license amendment application proposes to modify LC 59 to change the completion dates for three site reclamation milestones. The new dates proposed by Umetco would extend completion of (1) placement of final radon barrier on the A-9 impoundment by three years, (2) placement of erosion protection on the A-9 impoundment by three years, and (3) projected completion of groundwater corrective actions by four years.