Energie en milieu · 2-6-20251 min lezen
Southern Nuclear Operating Company, Inc.; Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2; Subsequent License Renewal Application
Lokale automatische vertaling · Oorspronkelijke brontaal
Samenvatting
The U.S. Nuclear Regulatory Commission (NRC) has received an application for the subsequent renewal of Renewed Facility Operating License Nos. DPR-57 and NPF-5, which authorize Southern Nuclear Operating Company, Inc. (Southern, the applicant) to operate Edwin I. Hatch Nuclear Plant (Hatch), Unit Nos. 1 and 2. The subsequent renewed licenses would authorize the applicant to operate Hatch for an additional 20 years beyond the period specified in each of the current licenses. The current operating licenses for Hatch expire as follows: Unit No. 1 on August 6, 2034, and Unit No. 2 on June 13, 2038.