Notice of Availability of Amended Record of Decision for Issuing a Presidential Permit to Energia Sierra Juarez U.S. Transmission, LLC, for the Energia Sierra Juarez U.S. Transmission Line Project

ローカル自動翻訳 · 情報源の原言語

概要

The Grid Deployment Office (GDO) of the Department of Energy (DOE) gives notice of an Amended Record of Decision (ROD) published under the National Environmental Policy Act of 1969 (NEPA) and DOE's NEPA implementing regulations. This Amended ROD supports DOE's decision to amend the existing Presidential permit issued to Energia Sierra Juarez U.S. Transmission, LLC (ESJ), to construct, operate, maintain, and connect a double-circuit, 230,000-volt (230-kV) electric transmission line (ESJ Tie Line) across the U.S.-Mexico border in eastern San Diego County, California.

情報源の原言語: Federal Register — All Documents原文の発表を開く →