Record of Decision for Issuing a Presidential Permit to Energia Sierra Juarez U.S. Transmission, LLC, for the Energia Sierra Juarez U.S. Transmission Line Project

Traduzione automatica locale · Lingua originale della fonte

Riepilogo

DOE announces its decision to issue a Presidential permit to Energia Sierra Juarez U.S. Transmission, LLC (ESJ), to construct, operate, maintain, and connect a double-circuit, 230,000-volt (230-kV) electric transmission line across the U.S.-Mexico border in eastern San Diego County, California. The potential environmental impacts associated with the transmission line are analyzed in the Environmental Impact Statement for the Energia Sierra Juarez U.S. Transmission Line Project (DOE/EIS-0414). The transmission line would originate at San Diego Gas and Electric's planned East County Substation (ECO Substation), and extend southward approximately 0.65 miles to the U.S. border with Mexico, near Jacumba, California, where it would cross the border and connect with a transmission line to be built in Mexico.

Lingua originale della fonte: Federal Register — Energy DepartmentApri il comunicato originale →