In the Matter of Kairos Power LLC; Hermes Test Reactor; Extension of Latest Date for Completion of Construction

Traduction automatique locale · Langue originale de la source

Résumé

The U.S. Nuclear Regulatory Commission (NRC) has approved the Kairos Power LLC (Kairos) request to amend Construction Permit No. CPTR-6 for the Hermes test reactor facility in Oak Ridge, Tennessee. The approved amendment extends the latest date for completion of the construction of the Hermes test reactor facility from December 31, 2026, to April 30, 2029.

Langue originale de la source: Federal Register — Nuclear Regulatory CommissionOuvrir le communiqué original →