Energía y medio ambiente · 5/1/20101 min de lectura

Notice of Intent To Prepare an Environmental Impact Statement for the Sigurd-Red Butte Transmission Line Project (Project) in Utah

Traducción automática local · Idioma original de la fuente

Resumen

In compliance with the National Environmental Policy Act (NEPA) of 1969, as amended, and the Federal Land Policy and Management Act of 1976, as amended, the Bureau of Land Management (BLM) Cedar City Field Office, Cedar City, Utah, intends to prepare an Environmental Impact Statement (EIS) for a right-of-way (ROW) application for the Sigurd-Red Butte 345 kilovolt (kV) Transmission Line Project and by this notice is announcing the beginning of the scoping process to solicit public comments and identify issues.

Idioma original de la fuente: Federal Register — Interior DepartmentAbrir el comunicado original →