Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Resolution of Auxiliary Building Wall Thickness and Description Inconsistencies

Lokale automatische Übersetzung · Originalsprache der Quelle

Zusammenfassung

The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption to allow a departure from the certification information of Tier 1 of the generic design control document (DCD) and issued License Amendment Nos. 103 and 102 to Combined License (COL) Nos. NPF-91 and NPF-92. The COLs were issued to Southern Nuclear Operating Company, Inc., and Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia (the licensee); for construction and operation of the Vogtle Electric Generating Plant (VEGP), Units 3 and 4, located in Burke County, Georgia. The granting of the exemption allows the changes to Tier 1 information asked for in the amendment. Because the acceptability of the exemption was determined in part by the acceptability of the amendment, the exemption and amendment are being issued concurrently.

Originalsprache der Quelle: Federal Register — Nuclear Regulatory CommissionOriginalquelle öffnen →

Weitere Themen

Business-Analysen →