Energie & Umwelt · 24.10.20131 Min. Lesezeit

Virgil C. Summer Nuclear Station, Units 2 and 3; South Carolina Electric and Gas; Changes to the Primary Sampling System

Lokale automatische Übersetzung · Originalsprache der Quelle

Zusammenfassung

The U.S. Nuclear Regulatory Commission (NRC) is granting an exemption to allow a departure from the certification information of Tier 1 of the generic design control document (DCD) and issuing License Amendment No. 8 to Combined Licenses (COL), NPF-93 and NPF-94. The COLs were issued to South Carolina Electric and Gas (SCE&G) and South Carolina Public Service Authority (Santee Cooper) (the licensee), for construction and operation of the Virgil C. Summer Nuclear Station (VCSNS), Units 2 and 3 located in Fairfield County, South Carolina. The amendment requests to modify the Primary Sampling System (PSS) design, including changes to Tier 1 information located in Tables 2.2.1-2, 2.3.13-1, and 2.3.13-3, Figures 2.2.1-1 "Containment System" and 2.3.13-1 "Primary Sampling System," and Subsection 2.3.13, "Primary Sampling System" of the Updated Final Safety Analysis Report (UFSAR). The granting of the exemption allows the changes to Tier 1 information asked for in the amendment. Because the acceptability of the exemption was determined in part by the acceptability of the amendment, the exemption and amendment are being issued concurrently.

Originalsprache der Quelle: Federal Register — Nuclear Regulatory CommissionOriginalquelle öffnen →