Energia i regulacje · 21.08.2013
AUC, LLC Reno Creek, In Situ Project, New Source Material License Application
By letter dated October 3, 2012, AUC, LLC (AUC) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for a new source material license. The requested license, or the proposed action, would authorize the construction and operation, and decommissioning of AUC's proposed in-situ uranium recovery (ISR, also known as in-situ leach) facilities, and would require restoration of the aquifer from which the uranium would be extracted. The proposed facility will be located near the town of Wright, Wyoming in Campbell County. The application was accepted for review by NRC on June 18, 2013. A notice of receipt and availability of the license application, including the Environmental Report (ER), and opportunity to request a hearing was published in the Federal Register on August 5, 2013 (78 FR 47427).