Drawbridge Operation Regulation; Chambers Creek, Steilacoom, WA
The Coast Guard has issued a temporary deviation from the operating schedule that governs the Burlington Northern Santa Fe (BNSF) Chambers Creek Railway Bridge across Chambers Creek, mile 0.0, at Steilacoom, WA. The deviation is necessary to allow BNSF to perform maintenance and upgrade items to this vertical lift bridge in support of Positive Train Control requirements per the Rail Safety Improvement Act of 2008. This will require locking the bridge in the closed position and locking out the power to the drive system while the work is conducted. This deviation allows the bridge to remain in the closed position for 45 days during the maintenance and upgrade work.