الطاقة والبيئة · 22/1/20261 دقائق للقراءة
Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2; Surry Power Station, Units 1 and 2; Withdrawal by Applicant
ترجمة آلية محلية · اللغة الأصلية للمصدر
الملخص
The U.S. Nuclear Regulatory Commission (NRC) is announcing the withdrawal of a license amendment application from Virginia Electric Power Company (the licensee), dated May 16, 2025, for a proposed amendment to North Anna Power Station, Units 1 and 2, and Surry Power Station, Units 1 and 2, License Nos. NPF-4 and NPF-7, and DPR-32 and DPR-37. The proposed amendment would have updated the Main Steam Line Break Alternate Source Term dose consequence analysis for both sites.