Virginia Electric and Power Company; Dominion Energy Virginia; Surry Power Station, Unit Nos. 1 and 2

ترجمة آلية محلية · اللغة الأصلية للمصدر

الملخص

The U.S. Nuclear Regulatory Commission (NRC) is considering an application for the subsequent license renewal of Renewed Facility Operating License Nos. DPR-32 and DPR-37, which authorize Virigina Electric and Power Company (Dominion Energy Virginia or the applicant) to operate Surry Power Station (SPS), Unit Nos. 1 and 2. The renewed licenses would authorize the applicant to operate SPS for an additional 20 years beyond the period specified in each of the current renewed licenses. The current renewed operating licenses for SPS expire as follows: Unit 1 on May 25, 2032, and Unit 2 on January 29, 2033.

اللغة الأصلية للمصدر: Federal Register — Nuclear Regulatory Commissionافتح البيان الأصلي →