In the Matter of Duke Energy Progress, Inc., and North Carolina Eastern Municipal Power Agency; Shearon Harris Nuclear Power Plant, Unit 1

ترجمة آلية محلية · اللغة الأصلية للمصدر

الملخص

The U.S. Nuclear Regulatory Commission (NRC) is issuing an Order to Duke Energy Progress, Inc. (Duke Energy) and North Carolina Eastern Municipal Power Agency (NCEMPA) approving the direct transfer of control of the Renewed Facility Operating License No. NPF-63, and ownership interest for the Shearon Harris Nuclear Power Plant (Harris), Unit 1, to the extent currently held by NCEMPA. As a result of the transaction, Duke Energy will become the sole owner of the Harris facility and hold 100 percent ownership of the facility. The conforming license amendment will remove references to NCEMPA. No physical changes to the facility or operational changes were proposed in the application and Duke Energy will remain as the licensed operator of the facility. This Order is effective upon issuance.

اللغة الأصلية للمصدر: Federal Register — Nuclear Regulatory Commissionافتح البيان الأصلي →

استكشف الموضوعات

تحليلات الأعمال →