Energia i gospodarka · 3/23/2011
Mandatory Reliability Standards for Interconnection Reliability Operating Limits
Under section 215 of the Federal Power Act, the Federal Energy Regulatory Commission (Commission) approves three new Interconnection Reliability Operations and Coordination Reliability Standards and seven revised Reliability Standards related to Emergency Preparedness and Operations, Interconnection Reliability Operations and Coordination, and Transmission Operations. These Reliability Standards were submitted to the Commission for approval by the North American Electric Reliability Corporation (NERC), which the Commission has certified as the Electric Reliability Organization responsible for developing and enforcing mandatory Reliability Standards. The Reliability Standards were designed to prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection by ensuring that the reliability coordinator has the data necessary to assess its reliability coordinator area during the operations horizon and that it takes prompt action to prevent or mitigate instances of exceeding Interconnection Reliability. Operating Limits. The Commission also approves the addition of two new terms to the NERC Glossary of Terms. In addition, th