Requirement R1.3.10 of the Commission-approved transmission planning Reliability Standard TPL-002-0 provides that planning authorities and transmission planners must consider in their planning studies the effects of the operation of their protection systems, including backup and redundant protection systems. The North American Electric Reliability Corporation (NERC), the Commission-certified electric reliability organization, requests approval of an interpretation of Reliability Standard TPL-002-0. In this order, the Commission proposes to reject NERC's proposed interpretation of Requirement R1.3.10 of Reliability Standard TPL-002-0 and, instead, proposes an alternative interpretation of the provision.