Energia i regulacje · 14.01.2015
Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station Post-Shutdown Decommissioning Activities Report
On December 23, 2014, the U.S. Nuclear Regulatory Commission (NRC) received the Post-Shutdown Decommissioning Activities Report (PSDAR) and the Site-Specific Decommissioning Cost Estimate (DCE) dated December 19, 2014, for the Vermont Yankee Nuclear Power Station (VY). The PSDAR, which includes the DCE, provides an overview of Entergy Nuclear Operations, Inc. (Entergy or the licensee), planned decommissioning activities, schedule, projected costs, and environmental impacts for VY. The NRC is requesting public comments on Entergy's PSDAR and DCE and will hold a public meeting to discuss the PSDAR and DCE.