The U.S. Nuclear Regulatory Commission (NRC) has received an application dated September 5, 2015, from Exelon Generation Company, LLC, for amendment of Clinton Power Station, Unit 1. The application proposes a one-time extension from 72 hours to 7 days of the technical specification (TS) completion time [CT] associated with the Division 2 (Div. 2) Shutdown Service Water (SX) Subsystem in support maintenance activities.