Administracja i zamówienia · 22.06.1998

Federal Acquisition Regulation; No-Cost Value Engineering Change Proposals

The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council have agreed on an interim rule amending the Federal Acquisition Regulation (FAR) to clarify that no-cost value engineering change proposals (VECPs) may be used when, in the contracting officer's judgment, reliance on other VECP approaches likely would not be more cost-effective, and the no-cost settlement would provide adequate consideration to the Government. This regulatory action was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993, and is not a major rule under 5 U.S.C. 804.

Source: Federal Register — General Services AdministrationOpen original release →