Energia i gospodarka · 24.11.2010
System Restoration Reliability Standards
Under section 215 of the Federal Power Act (FPA), the Federal Energy Regulatory Commission (Commission) proposes to approve Reliability Standards EOP-001-1 (Emergency Operations Planning), EOP- 005-2 (System Restoration from Blackstart Resources), and EOP-006-2 (System Restoration Coordination) submitted to the Commission by the North American Electric Reliability Corporation, the Electric Reliability Organization (ERO) certified by the Commission. In addition, the Commission seeks comment from the ERO and other interested parties regarding specific concerns. The Commission may determine that, after considering such comments, it is appropriate to direct the ERO, under section 215(d)(5) of the FPA, to develop additional modifications to proposed EOP-005-2 and EOP-006-2. The proposed Reliability Standards require that plans, facilities and personnel are prepared to enable system restoration using designated blackstart resources.