Energia i regulacje · 20.08.2019
Entergy Nuclear Operations Inc; Pilgrim Nuclear Power Station
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption in response to a November 16, 2018, request from Entergy Nuclear Operations, Inc. (ENOI or the licensee) on behalf of Entergy Nuclear Generation Company (ENGC) (to be renamed Holtec Pilgrim, LLC) and Holtec Decommissioning International, LLC (HDI), related to Pilgrim Nuclear Power Station (Pilgrim), located in Plymouth County, Massachusetts. The proposed action would permit Holtec Pilgrim, LLC and HDI to use funds from the Pilgrim decommissioning trust fund (the Trust) for management of spent fuel and site restoration activities. The staff is issuing a final environmental assessment (EA) and a final finding of no significant impact (FONSI) associated with the proposed exemption.