Energia i regulacje · 19.11.2019
Power Reactor In-Core Monitoring
The U.S. Nuclear Regulatory Commission (NRC) is denying a petition for rulemaking (PRM), dated March 13, 2015, submitted by Mark Edward Leyse (petitioner). The petition was docketed by the NRC on April 24, 2015, and assigned Docket No. PRM-50-111. The petitioner requested that the NRC require all holders of operating licenses for nuclear power plants to operate them with in-core temperature- monitoring devices (e.g., thermoacoustic sensors or thermocouples) located at different elevations and radial positions throughout the reactor core. The NRC is denying the petition because current regulations provide a sufficient level of safety, such that additional requirements for in-core temperature-monitoring devices as specified in the petition are not needed.