Regulacje i polityka gospodarcza · 22.10.2015
Proposed Settlement Agreement
In accordance with section 113(g) of the Clean Air Act (the "Act"), 42 U.S.C. 7413(g), notice is hereby given of a proposed settlement agreement to resolve two cases filed by the WildEarth Guardians ("Guardians") and Sierra Club involving EPA actions under the CAA Title V operating permit program. On January 7, 2015, Guardians and Sierra Club filed petitions with the Environmental Appeal Board ("EAB") challenging a Part 71 Operating Permit issued by EPA Region 8 on December 5, 2014, to Deseret Power Cooperative ("Deseret") to operate the Bonanza Power Plant ("Bonanza Plant") (In re Deseret Power Cooperative Bonanza Power Plant, CAA Appeal Nos. 15-1, 15-2). Under the proposed settlement agreement, Deseret would submit an application for a minor New Source Review (NSR) permit to implement the specific terms of the agreement; and EPA would draft and provide for public notice of the proposed permit.