Completion Date of Cyber Security Plan Implementation Milestone 8; Tennessee Valley Authority; Sequoyah Nuclear Plant, Units 1 and 2
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of amendments to Facility Operating License Nos. DPR-77 and DPR-79, issued to the Tennessee Valley Authority, for operation of the Sequoyah Nuclear Plant (SQN), Units 1 and 2. The proposed amendments would revise the SQN, Units 1 and 2, Cyber Security Plan (CSP) implementation schedule for Milestone 8 and would revise the associated license condition in the Facility Operating Licenses. The amendment request contains sensitive unclassified non-safeguards information (SUNSI).