On April 23, 2007, Entergy Operations, Inc. (Entergy), submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for renewal of Facility Operating Licenses DPR-26 and DPR- 64 for an additional 20 years of operation at Indian Point Nuclear Generating Units 2 and 3 (IP2 and IP3). The current operating licenses for IP2 and IP3 expire on September 28, 2013, and December 12, 2015, respectively. The purpose of this document is to inform the public that the NRC will be preparing a supplement to the final Supplemental Environmental Impact Statement (SEIS) to address information on aquatic impacts in accordance with the NRC's regulations.