Drawbridge Operation Regulations; Kennebec River, ME
The Coast Guard proposes to temporarily change the drawbridge operating regulations governing the operation of the Carlton Bridge, mile 14.0, across the Kennebec River between Bath and Woolwich, Maine. This proposed rule would allow the bridge to open on signal every three hours at 6 a.m., 9 a.m., 12 p.m., 3 p.m., and 6 p.m., Monday through Saturday, from July 5 through December 17, 2005, and again from April 1 through June 30, 2006, to facilitate rehabilitation construction at the bridge. This rule also would allow five three-day bridge closures in September and October of 2005. Vessels that can pass under the bridge without a bridge opening may do so at all times.