BN Business News
Add your company to Business Communicator →

Energia i infrastruktura · 19.12.2005

Interconnection for Wind Energy

The Federal Energy Regulatory Commission is granting in part and denying in part the requests for rehearing and clarification of its Final Rule on Interconnection for Wind Energy, Order No. 661. Order No. 661 requires public utilities that own, control, or operate facilities for transmitting electric energy in interstate commerce to append to their standard large generator interconnection procedures and large generator interconnection agreements in their open access transmission tariffs standard procedures and technical requirements for the interconnection of large wind generation.

Source: Federal Register — Federal Energy Regulatory CommissionOpen original release →