MOAB Mill Reclamation Trust

Notice is hereby given that the U.S. Nuclear Regulatory Commission (NRC) has received, by letter dated March 31, 2000, a request from Moab Mill Reclamation Trust to amend License Condition (LC) 55 A and B of Source Material License SUA-917 for the Moab, Utah, facility. The license amendment request proposes to modify LC 55 A.(1) to change the completion date for placement of the windblown tailings on the pile to December 31, 2001; LC 55 A.(3) to change the completion date for placement of the final radon barrier on the pile to December 31, 2002; LC 55 B.(1) to change the completion date for placement of the erosion protection on the pile to June 30, 2003; and LC 55 B.(2) to change the completion date for ground-water corrective actions to July 31, 2008.

Source: Federal Register — Nuclear Regulatory CommissionOpen original release →