BN Business News
Add your company to Business Communicator →

Regulacje i polityka gospodarcza · 15.12.1999

Boulder Canyon Project-Base Charge and Rates

Notice is given of the confirmation and approval by the Deputy Secretary of the Department of Energy (DOE) placing the Base Charge and Rates for the Boulder Canyon Project (BCP) firm power into effect for the fifth rate year under the current rate methodology pursuant to Rate Schedule BCP-F5 as approved by the Federal Energy Regulatory Commission (FERC) on April 19, 1996 (Rate Order No. WAPA-70). The Base Charge will provide sufficient revenue to pay all annual costs, including interest expense, and repayment of required investment within the allowable period.

Source: Federal Register — All DocumentsOpen original release →