Federal Acquisition Regulation; Independent Government Estimates- Construction

The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council have agreed on a final rule amending the Federal Acquisition Regulation (FAR) to increase the threshold for a mandatory independent Government estimate of construction costs and architect-engineer costs from $25,000 to $100,000. This regulatory action was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993, and is not a major rule under 5 U.S.C. 804.